NR-364 Nong Nam Sai - Pang Ko Road

Construction Contract for Roadworks (11 Items)
Purpose: For the construction of Highway No. 2256, Section: Nong Nam Sai – Pang Ko, between km 29+350 to km 32+150, with a total distance of 2.800 kilometers.

Contract No.: SLS./M.2(J)/25/2566 dated 19 January 2023
Contract Start Date: 20 January 2023
Contract End Date: 10 August 2023
Duration: 203 days
Contract Value: 62,234,200.00 THB